BuildingPlans.co.za

Building plans in Tshwane (Pretoria)

How building plans are submitted to the City of Tshwane, what it charges, where its offices are, and what to check before you start.

City of TshwaneBuilding control
Submission
NAPS on e-Tshwane
Plan fee
R23 per m², min R920
Tariff year
2025/26, latest found
Decision
30 days under 500 m²

How plans are submitted

Tshwane launched NAPS, its New Applications Processing System, on the e-Tshwane portal in December 2024. Through it, plans for building approval, demolition, site development plans, rezoning and additional dwelling houses can be submitted online. You need a municipal account number to register on e-Tshwane.

At launch the city said NAPS would start in Region 1 (Akasia and Soshanguve) and Region 4 (Centurion), with the other regions to follow once connectivity and hardware were in place. We found no newer statement on the rollout, so check with the city for your region before you assume either way.

e-Tshwane support: support@e-tshwane.co.za, 0861 444 779.

Tshwane's regions

RegionAreas
1Akasia, Soshanguve
2Montana, Pretoria North, Hammanskraal
3Inner city, Pretoria West, Old East
4Centurion
5Rayton
6Eersterust, New East
7Cullinan

What it costs

Tshwane's building plan fees are in Schedule 16 of its tariffs, gazetted for 2025/26 (VAT included). We found no 2026/27 building plan schedule on the city's tariff page when we checked.

ItemFee
New building or additionR23 per m², minimum R920
Alteration with no extra floor areaR920
Amended plan, no extra areaR920
Renewal of a lapsed approvalR920
Minor building work exemption (section 13)R920
Starting to build before approval, section 7(6)R12 per m², minimum R920
Re-inspectionR460
Building line relaxation, erf over 500 m²R1 100
Building line relaxation, erf 500 m² or smallerR550

Walls up to 2.1 m, pergolas, swimming pools and other unroofed structures are not counted in the floor area, so for those the minimum fee is what applies. Fees are paid on submission and are not refundable, except where the city miscalculated the fee.

Work out a fee with the plan fee calculator.

Offices

The addresses below are from city documents and news reports, some dating from 2020. Councils move counters, so phone first.

  • Tshwane Building Control, Isivuno House, 143 Lilian Ngoyi Street, Pretoria Central
  • Centurion municipal complex (Region 4), corner Basden Avenue and Rabie Street, Lyttelton
  • Akasia municipal complex (Region 1), 16 Dale Avenue, Karenpark
  • Soshanguve municipal building (Region 1), 2275 Block F
  • Kudu House, Sinoville municipal complex, 240 Marija Street
  • Chris Hani building, Cullinan (Region 7)

Zoning lookup

The Tshwane e-GIS viewer lets you search by erf, street address or township and see the zoning layer: e-gis003.tshwane.gov.za. The viewer is indicative. The official zoning certificate comes from the city.

How long it takes

The Act gives the city 30 days to decide on plans under 500 m² and 60 days for larger ones, counted from receipt of the application. A 2025 statement relayed by ActionSA says NAPS cut the average for residential plans under 500 m² from 30 days to 14 days in Regions 1 and 4. We found no official measured figure for 2026.

Questions people ask

Can I submit building plans online in Tshwane?

In some regions. NAPS on e-Tshwane launched in December 2024 for Regions 1 (Akasia, Soshanguve) and 4 (Centurion). Check with the city whether your region is on it.

How much are building plan fees in Tshwane?

Under the 2025/26 tariff, R23 per square metre for a new building or addition, with a minimum of R920 (VAT included).

How do I find my zoning in Tshwane?

Search your erf or address on the Tshwane e-GIS viewer. For a submission you need the official zoning certificate from the city.

Sources

  1. City of Tshwane: NAPS launch statement
  2. City of Tshwane: land and building applications
  3. City of Tshwane: promulgated tariffs (2025/26, Schedule 16)
  4. City of Tshwane: regions
  5. City of Tshwane: Region 4
  6. e-Tshwane
  7. Tshwane e-GIS viewer
  8. Tshwane trade and investment process booklet 2020/21 (TEDA)
  9. Pretoria Institute for Architecture: Tshwane Building Control notice
  10. Rekord: Tshwane opens development and spatial planning offices (2020)
  11. ActionSA statement on Tshwane plan processing times
  12. National Building Regulations and Building Standards Act 103 of 1977 (copy on CPMS)

Checked October 2026. Councils change their tariffs every July, so confirm fees before you pay.

WhatsApp us about your plans