Do I need building plans for replacing a roof?

Depends

Replacing a roof with the same or similar material is minor building work. A different, heavier covering or a new roof structure needs plans.

Replacing a roofDo I need plans?
Answer
Depends
Rule
SANS 10400-A, Reg A1(b)
Limits
Like for like only
Checked
October 2026

"The replacement of a roof or part of a roof with the same or similar material" is minor building work. Johannesburg lists like-for-like roof replacement on its exemption list.

You still apply to the council for authorisation before you start. A repair in the normal course of maintenance needs nothing.

Changing to a heavier covering (sheeting to tiles, for example), to thatch, or changing the roof's shape or trusses needs plans and usually an engineer to check the structure. Thatch brings SANS 10400-T's fire-distance rules, and new roof insulation falls under SANS 10400-XA.

Sources

  1. SANS 10400-A:2010, Regulations A1 and A2 (minor building work)
  2. City of Johannesburg CPMS submission checklists (minor works list)
  3. SANS 10400-T:2011, fire protection (thatched lapas)

Checked October 2026. Councils change their tariffs every July, so confirm fees before you pay.